Project Details:
South Burlington, VT
Dental Office Fit-Up
Project Overview:
A 2,700 SF dental office fit-up consisting of a reception area, four endodontic procedure rooms, support space, and improvements for Sirona 3D X-ray equipment
Our work to fit up the space for Vermont Endodontics occurred in an occupied medical office facility, requiring careful awareness and planning to minimize any impact to the surrounding practices. Close coordination with the client, along with a detailed schedule with the dental equipment supplier, provided for a smooth integration and installation of the dental equipment.
Building infrastructure improvements included the installation of a high-efficiency cooling tower and additional heat pumps. Compressed air, vacuum, and distilled water systems were installed and distributed to each procedure room.