Project Details:
Williston, Vermont
Facility Upgrades
Project Overview:
A construction project consisting of improvements and upgrades to two existing pump stations within a municipal wastewater facility
To accomplish the structural improvements to Williston’s pump stations, detailed pre-construction planning was a critical first step to ensure the safe, ongoing operation of the facility. Close communication with the plant operators was then required throughout the operation. Together, we coordinated a plan for 100% by-pass pumping of Williston’s total wastewater capacity, which was required to complete the upgrades to the first facility.
All new process systems were included at both pump stations, including pumps, controls, VFDs, piping, and new emergency power systems.