The Neagley & Chase Construction Team is proud to announce the results of the final envelope commissioning report for the North Country School Performing Arts Project. The following quote sums up the entire team’s efforts and results to a tee.
“The Neagley & Chase team was committed to the Performance Center meeting the Passive House air tightness standard of 0.05 CFM50/sf. There were challenges along the way: Winter, new products, and materials not performing as expected. They adapted to every challenge with innovation and attention to detail. The building surpassed the target at 0.027 CFM50/sf. Nice work NCC!”
- Jon Haehnel, Director of Building Envelope Services, BVH Integrated Services, P.C.
Kudos and congratulations to the entire project team, with a special shout-out to the NCC team in the field – stellar job!
Learn more about the Walter Breeman Performing Arts Center here:
https://www.neagleychase.com/case_study/performing-arts-center-at-the-north-country-school/
Learn more about NCC’s successful approach to delivering high performance envelopes here:
https://www.neagleychase.com/delivering-a-high-performance-envelope/